We want to ensure that even with current COVID-19 restrictions the local community can continue to receive important updates on construction works in your area.

Sign up for email alerts of all work notifications occurring in your area.

Below you can find a list of recent notifications we have delivered to the:

Visit our disruptions page for the latest traffic updates.

WhereWhenWhatNotification
Newport Rail Bridge, Yarraville / South KingsvilleEarly November 2020Installing the new barriers onto the bridge and pouring concrete to connect the barriers to the bridge surface. Works moved from October to early November.September 2020:
PDF (208KB)
DOCX (289KB)
Williamstown Road & Blackshaws RoadSeptember - early October 2020Detour information for closures on the West Gate Freeway.September 2020:
PDF (196KB) 
Rosala Avenue walking and cycling overpass, Altona NorthSeptember - November 2020Installing the new walking and cycling overpass over the West Gate Freeway between Rosala Avenue and Richards Court. September 2020:
PDF (204KB)
DOCX (297)
Millers Road freeway interchange, Altona North / BrooklynLate August - Early October 2020Extended closures of the Millers Road inbound exit and entry ramps and four week closure of Millers Road under the freeway. Hydro blasting will occur in late September.

Local road access changes at Primula Avenue, Beevers Street and Cypress Avenue.

September 2020:
PDF (346KB)
DOCX (370KB)

August 2020:
PDF (267KB)
DOCX (1.1MB)

Dohertys Road, Altona NorthAugust 2020 - mid April 2021Relocating a water main along Dohertys Road as part of the M80 Ring Road upgrade.August 2020:
PDF (307KB)
DOCX (301KB)
Fogarty Avenue, YarravilleJune - mid November 2020The Boulevard works will now be completed by mid-November and this section of road reopened. This does not affect through traffic from The Avenue. June 2020:
PDF (384KB)
DOCX (396KB)
Fogarty Avenue, YarravilleLate July to late 2020Temporary traffic changes on Fogarty Avenue, as part of works to connect the new drainage pipes to the West Gate Freeway system. Sections of Fogarty Road will be temporarily closed.July 2020:
PDF (345KB)
DOCX (360KB) 
Hyde Street ramps, SpotswoodJuly 2020 - ongoingConstruction of new Hyde Street ramps from the north and south side of the freeway are progressing. Works on the elevated shared use paths and bridges will also continue.July 2020:
PDF (421KB)
DOCX (411KB) 
Muir Street, Spotswood & Fogarty Avenue, YarravilleJuly - November 2020Building new pedestrian overpass over West Gate Freeway between Muir Street & Fogarty Avenue and installing new noise walls.July 2020 - North side: 
PDF (193KB)
DOCX (417KB) 

July 2020 - South side: 
PDF (226KB)
DOCX (326KB)
Williamstown Road to Newport Rail Line, Spotswood, Yarraville, South KingsvilleJuly 2020 - ongoing Williamstown Road utilities and road widening works. Continued works to widen and strengthen the Newport Rail Bridge will also occur.   July 2020:

PDF (450KB)
DOCX (504KB)
Fogarty Avenue, YarravilleJuly 2020 - ongoingPiling and construction of new shared user paths.July 2020:

PDF (336KB)
DOCX (738KB)
Williamstown Road to Newport Rail Line, Spotswood, Yarraville, South KingsvilleJune 2020 - ongoingInstalling the concrete noise wall panels along the West Gate Freeway.June 2020:

PDF (752KB)
DOCX (809KB)
Noise wall installation updatesOngoingThe West Gate Tunnel Project includes building 9km of new noise walls along the West Gate Freeway.

As well as being more attractive, the new noise walls will provide you much better protection from freeway noise than the old noise walls.
Williamstown Road to the Newport Rail Bridge:
PDF (377KB)
DOCX (897KB)


Fogarty Avenue:
PDF (500KB)
DOCX (477KB)
Hyde Street Ramps, SpotswoodFebruary 2020 - ongoingAs part of works on the West Gate Tunnel Project, we will be building two new ramps for the West Gate Freeway.February 2020:
PDF (544KB)
DOCX (444KB)
New Street and Watson Street, South KingsvilleJune 2019 - ongoingSite establishment at the end of New and Watson Street, South Kingsville. These works are the construction of the West Gate Tunnel outbound southern portal.

May 2019:

PDF (521KB)
DOCX (950KB)

West Gate Freeway (outbound) between Chambers Road and Grieve Parade, Altona, Altona North16 November 2018 – ongoingWorks to widen the West Gate Freeway between Chambers Road and Grieve Parade and provide new noise walls.

November 2018:

PDF (795KB)
DOCX (568KB)

Kyle Road, Altona NorthThursday 11 October 2018 – ongoingUse of Kyle Road to access construction sites on the West Gate Freeway for the duration of the project’s construction.

September 2018:

PDF (258KB)
DOCX (747KB)

West Gate Freeway: Williamstown Road inbound exit ramp, SpotswoodFrom 29 May 2018 – ongoingWorks along both sides of the West Gate Freeway between The Avenue and Williamstown Road, including vegetation removal and installing temporary fencing.
Installation of temporary and new noise wall along Williamstown Road inbound exit ramp.
May 2018:

PDF (274KB)
DOCX (488KB)

West Gate Freeway (outbound) between Williamstown Road and The Avenue, Spotswood and YarravilleFrom 29 May 2018 – ongoing
  • Temporary road closures between Vernier Street and Hick Street, and between Andrews Street and Muir Street.
  • Site fencing and access established at the end of the following streets: Abbot Street, Steel Street, Vernier Street, Hick Street, Andrews Street, Muir Street.
  • Site establishment works along outbound lanes of West Gate Freeway, including vegetation removal and earthworks.
  • Installation of temporary and new noise wall between Vernier Street and Muir Street.
  • Relocate existing power lines that currently run along the West Gate Freeway to the reserve near the corner of The Avenue and Strong Street.

Overview:
PDF (277KB)

DOCX (493KB)

WhereWhenWhatNotification
New Street worksite, South KingsvilleNovember 2019 - 2020Works continue at our southern portal site, where the outbound tunnel will meet the West Gate Freeway, to establish our construction site at the end of New and Watson streets, South Kingsville.

For four weeks from early-November, we will demolish three low-rise brick buildings and two steel sheds containing asbestos cladding within the site. All asbestos will be removed in accordance with the safety approved procedures and standards by a fully licensed and approved asbestos contractor.
October 2019 update:

PDF (451KB)
DOCX (286KB)
Whitehall Street construction areas, Yarraville and FootscrayDecember 2018 - ongoingOngoing and planned work at Whitehall Street construction sites, including:
  • delivering the Tunnel Boring Machines
  • overnight lane closures, temporary lane closures and other short term traffic changes on Whitehall Street from January 2019
  • continued excavation at the Northern Portal site
  • continuing construction on the big shed at 221 Whitehall Street
  • utility relocation on Maribyrnong Street, Lyons Street and Whitehall Street in preparation for Maribyrnong River bridge works early next year.
March 2019 update:
PDF (2.6MB)
DOCX (2.5MB) 

December 2018 update:
PDF (1.7MB)
DOCX (697KB)

Tunnels precinct (Whitehall Street and Hyde Street, Yarraville and Footscray)April 2018 - ongoingPiling and increased activity at our Whitehall Street construction sites; utility investigations on Whitehall Street; intersection upgrades; North Yarra Main Sewer worksPDF (658KB)
DOCX (526KB)
Tunnels precinct (Whitehall Street, Yarraville and Footscray)March 2018 - ongoingOngoing work at Whitehall Street construction sitesPDF (492KB)
DOCX (389KB)
WhereWhenWhatNotification
Wurundjeri WaySeptember 2020We are building a Wurundjeri Way extension. Preparatory works have begun as we locate services and remove vegetation in preparation for gas relocation works from the west of La Trobe Street to the Footscray Road T-intersection.August 2020:
PDF (819KB)
DOCX (396KB)
Dynon RoadFebruary 2020 - ongoingConstruction of the new Dynon Road shared use path and bridges over
Moonee Ponds Creek.
June 2020:
DOCX (425KB)
Footscray RoadJanuary 2019 - ongoingWorks are progressing to build the new elevated road above Footscray Road with ongoing piling works and elevation of the Launching Gantry taking place in the centre median. Works on the new shared use paths are also taking place near Moonee Ponds creek and Docklands.June 2020:
PDF (142KB)
DOCX (387KB)
Maribyrnong StreetMarch 2020 - ongoingFrom late March, the project delivery team will be implementing traffic changes along Maribyrnong Street and Lyons Street to accommodate the next stage which will be in place for the next 24 months. March 2020:
PDF (325KB)
 Wurundjeri Way ExtensionFebruary 2020 - ongoingWorks to build the new Wurundjeri Way
Extension, an elevated road connecting to Dynon Road and the new elevated
Footscray Road that will link the West Gate Tunnel to the city.
February 2020:
PDF (305KB)
DOCX (314KB)
Maribyrnong RiverJanuary 2019 - ongoingWorks to construct the new bridges across the Maribyrnong River, linking the West Gate Tunnel to the elevated roadway above Footscray Road.

Changes to Maribyrnong Street:

  • removal of car parks on Maribyrnong Street, south of Parker Street
  • truncation of Maribyrnong and Lyons streets

February 2020 update:
PDF (345KB)
DOCX (325KB)


July 2019 update:
PDF (522KB)
DOCX (1666KB)

Port to City precinct2018 – 2022Introduction to upcoming construction in the Port to City precinct, including:
  • setting up the worksite on Footscray Road at the old Melbourne Market site
  • extending Wurundjeri Way to connect with Dynon Road
  • improving connections to the port and providing connections from the West Gate Freeway to CityLink and the CBD via an elevated road.
PDF (363KB)
DOCX (2.19MB)

West Gate Freeway

WhenWhenWhatNotification
Newport Rail Bridge, Yarraville / South Kingsville Early September - Early October Hyrdroblasting the concrete on the Newport Rail Bridge section of the West Gate Freeway above The Avenue. September 2020:
PDF (381KB)
DOCX (642KB)
West Gate Freeway / Don McLean Reserve, Spotswood July 2020Tree removals at Don McLean Reserve, Williamstown Road outbound entry ramp & West Gate Golf Course.June 2020:
PDF (172KB)
DOCX (306KB)
Fogarty Avenue, YarravilleMid June to early July 2020Fogarty Avenue will be temporarily closed in sections between Tenterden and Highgate streets. This does not affect through traffic from The Avenue.June 2020:
PDF (384KB)
DOCX (396KB)
Millers Road Interchange, BrooklynJune 2020Trees in the centre of the Millers Road interchange and near the Millers Road inbound entry ramps will be removed to allow for lane widening and realignment works. June 2020:
PDF (170 KB)
DOCX (301 KB)
Beevers Street, Altona NorthJune-July 2020Works to relocate a water main and rebuild a traffic island located across the entrance of Beevers Street. June 2020:
PDF (227KB)
DOCX (328KB)
Millers Road / West Gate Freeway April - August 2020Ongoing freeway widening works and hydro-blasting and installation of noise walls, retaining walls and bridge beamsApril 2020:
PDF (226KB)
Strong Street, SpotswoodFebruary - mid-July 2020We are diverting a large water main pipe that runs under the West Gate Freeway between the Footscray Hockey Club and Strong Street.

February 2020:
PDF (190KB)
DOCX (291KB)

June 2020:
PDF (41KB)

Strong Street, SpotswoodFebruary - late May 2020We are diverting a large water main pipe that runs under the West Gate Freeway between the Footscray Hockey Club and Strong Street.February 2020:
PDF (190KB)
DOCX (291KB)
Fogarty Avenue, YarravilleMonday 20 January - early May 2020 Fogarty Avenue will be closed between the Muir Street walking and cycling bridge and 216 Fogarty Avenue.

January - April 2020 summary:
PDF (441KB)
DOCX (496KB)

January 2020:
Driveway impacts
PDF (274KB)
DOCX (373KB)

Waste Collection
PDF (272KB)
DOCX (372KB)

Rosala Avenue / Richards Court overpass 23 May 2020To make way for widening the West Gate Freeway, we need to close and safely remove the existing pedestrian overpass that connects Rosala Avenue and Richards Court.May 2020
PDF (279 KB)
DOCX (536 KB) 
Muir Street / Fogarty Avenue overpass 23 May 2020To make way for widening the West Gate Freeway, we need to close and safely remove the existing pedestrian overpass that connects Muir Street and Fogarty Avenue.May 2020
PDF (282 KB)
DOCX (548 KB)
Williamstown Road inbound exit ramp closureMarch - April 2020Work is continuing to complete the relocation of a large underground sewer pipe at the Williamstown Road inbound exit ramp.March 2020:
PDF (279KB)
DOCX (390KB)
M80 Interchange ramp closuresJanuary - February 2020Ramp widening and reconstructionJanuary 2020:
PDF (280KB)
DOCX (558KB)
Millers Road areaOctober 2019 - February 2020West Gate Freeway widening and ramp reconstructionJanuary 2020:
Summer disruptions 
PDF (282KB)

October 2019:
Millers Road interchange 
PDF (215KB)
DOCX (288KB)

Paringa Road, Altona NorthMonday 9 December - Thursday 12 December and Wednesday 18 December 2019Paringa Road closed from Chambers Road to Langshaw Street for the delivery of new freeway safety barriers.December 2019:
PDF (318KB)
DOCX (306KB)

July 2019:

March 2019:

Stage two notifications

Stage one notifications

Beevers Street, Altona NorthJanuary - December 2019Drainage line works.December 2019:

PDF (255KB)
DOCX (334KB)

October 2019:

PDF (286KB)
DOCX (244KB)

Previous notifications:

  • Beevers Street utility relocation fact sheet (PDF, 2.10MB)
  • Reinstatement works, including full closure of Beevers Steet from Thursday 28 February - Saturday 2 March 2019 (PDF, 431KB)(DOCX, 794KB)

Stage three notifications

Stage two notifications

Stage one notifications

September 2018:

PDF (209KB)
DOCX (334KB)

Bena Street, YarravilleNovember 2019Water main works. November 2019:

Driveway access impacts:
PDF (657KB)
DOC (726KB)

No-driveway access impacts
PDF (469KB)
DOC (411KB)

Night works impacts:
DOC (1.08MB)

Millers Road / West Gate Freeway interchangeWednesday 24 October 2018 – March, 2019West Gate Freeway widening.

Upgrading Millers Rd underneath the freeway.

October 2018:

PDF (263KB)
DOCX (1MB)

Millers Road areaFrom June-August 2019 Centre median and bridge works. May 2019:

PDF (469KB) 
DOCX (273KB)

Buchanan Road, BrooklynNovember - December 2019Freeway widening and utilities relocation. October 2019:

PDF (283KB)
DOCX (291KB)

Strong Street, Spotswood30 September - early DecemberWater main works. September 2019:

PDF (310KB)
DOCX (1022KB)

Rosala Avenue & Richards Court, Altona North16 August - 8 September 2019Pedestrian bridge and freeway widening works. August 2019:

PDF (185KB)
DOCX (244KB)

Fogarty Avenue, Yarraville31 July 2018 – late December 2019Relocating some existing power lines, installing new drainage along Fogarty Avenue.
  • Staged closure - 7 August 2019 update: Fogarty and Wembley Avenue
    PDF (148 KB)
  • Temporary Closure between Cranbrook Street and Deleware Street (Until 31 May)
  • Between Footscray Hockey Club and Strong Street (until 27 March)
  • Power line relocation (26 March - 12 April) PDF (595KB)
    DOCX (705KB) 
Freemans Road,  Altona NorthFrom August - September 2019Noise walls installationAugust 2019:

PDF (239KB)
DOCX (421KB)

Italian Social Club, Altona North


Rosala Avenue, Altona North


Houston Court, Brooklyn

From July - October 2019Monopole and lattice tower installation. August 2019:
 
Rosala Ave 
PDF (456KB)
DOCX (770 KB)

June 2019:
PDF (476KB)
DOCX (782KB)

New Street and Watson Street, South KingsvilleFrom early June 2019Construction of the West Gate Tunnel outbound southern portal.May 2019:

PDF (521KB)
DOCX (950KB)

Williamstown Road / West Gate Freeway interchange and Fogarty AvenueMarch - May 2019Site establishment, sewer pipe diversion, ramp and bridge construction.PDF (189KB)
DOCX (1750KB)
Cullen Court, Spotswood7 February - early March 2019Sewer works.February 2019:

PDF (117KB)
DOCX (1005KB)

West Gate Freeway between Knapp St and Millers RdDecember 2019Community information sessionsNovember 2018:

PDF (757 KB)
DOCX (317 KB)

MAP (218 KB)

Kyle Road, Altona NorthThursday 11 October 2018 – 2022Construction site access. September 2018:

PDF (258KB)
DOCX (747KB)

Primula Avenue, BrooklynFrom 1 October 2018Vehicle access to Paringa Road from Millers Road will be closed long-term to allow for freeway widening works.September 2018:

PDF (247KB)
DOCX (385KB)

Buchanan Road and nearby Reserve, Brooklyn

Kyle Road, Altona North

20 September – mid-2019Moving 66kV power lines underground, including:

Replacing 220kV tower with a monopole, including:

Buchanan Road and nearby reserve:
PDF (242KB)

DOCX (414KB)


Kyle Road:
PDF (192KB)
DOCX (377KB)

Millers Road / West Gate Freeway interchangeFrom July 2018 – mid-2019Widening the freeway and upgrading the section of Millers Road under the freeway, including:July 2018:

PDF (385KB)
DOCX (396KB)

West Gate Freeway, between Williamstown Road and M80 interchangeJuly 2018Removal of overhead sign gantries and lighting structures.July 2018:

PDF (716KB)
DOCX (229KB)

Williamstown Road, under West Gate Freeway12 June – late JulyUpgrading Williamstown Road under the West Gate Freeway, including:
  • modifications to traffic signals, ramp signals and CCTV
  • removing traffic islands and installing temporary ones
  • earthworks and vegetation removal
  • general construction, asphalt construction and kerbing works
  • reinstating the road surface once works are completed.
May 2018:

PDF (830KB)
DOCX (391KB)

Millers Road / West Gate Freeway interchange20 May – June 2018Work starting around the Millers Road / West Gate Freeway interchange, in preparation for the widening of the freeway and upgrading Millers RoadMay 2018:

PDF (1MB)
DOCX (349KB)

Whitehall Street and Hyde Street, Yarraville and FootscrayMay and June 2018Day and night works as we prepare to divert a section of the North Yarra Main Sewer. May 2018:

PDF (625KB)
DOCX (573KB)

Williamstown Road, Yarraville and Spotswood12 May – December 2018Building a new inbound exit ramp and upgrading Williamstown Road, and establishing a construction site on Melbourne Road.April 2018:

PDF (255KB)
DOCX (229KB)

West Gate Freeway precinctFrom March 2018Building a temporary inbound exit ramp at Williamstown Road, widening the West Gate Freeway, continuing site investigationsMarch 2018:

PDF (550KB)
DOCX (1.9MB)

West Gate Freeway, between Wembley Ave and Williamstown RoadFrom February 2018Establishing work site, building a temporary exit ramp, roadworks and project investigations.February 2018:

PDF (600KB)
DOCX (500KB)

Tunnels

WhereWhenWhatNotification
Railway Place Reserve   December 2019 - February 2020To build the new shared use path along Dynon Road. November 2019:
PDF (641KB)
DOCX (410KB)
Whitehall Street Construction AreasFrom June-August 2019Construction area update.August 2019 update:
PDF (257KB)
DOCX (907KB)

June 2019 update:
PDF (1,379KB)
DOCX (1,288KB)

May 2019 update:
PDF (628KB)

Kent Street and Campbell Street, YarravilleFrom mid-June 2019Recharge well installationAugust 2019 update:
PDF (538KB)
DOCX (1.02MB)

May 2019 update:
PDF (628KB)

April 2019 update:
PDF (638KB)
DOCX (1,001KB)

Frederick Street, YarravilleFrom 6 May 2019Recharge well installationPDF (625KB)

Previous Updates:
PDF (838KB)

Whitehall Street and surrounding streets in Footscray and YarravilleFrom mid-May 2019Installing signals on Whitehall Street.PDF (794KB)

Previous Updates:PDF (616KB)
DOCX (1.72MB)
Whitehall Street construction areas, Yarraville and FootscrayFrom December 2018 Construction updates. PDF (2.6MB)


March 2019 update:
PDF (2.6MB)
DOCX (2.5MB) 

December 2018 update:
PDF (1.7MB)
DOCX (697KB)

Fredericks Street and York Street, YarravilleJuly – August 2018Geotechnical investigations and drilling a borehole both streets. Fredericks Street
PDF (710KB)
DOCX (1.8MB)
York Street
PDF (704KB)
DOCX (1.8MB)
33 Maribyrnong Street, FootscrayEarly July, for up to 3 monthsBuilding demolition and site establishment works at 33 Maribyrnong Street. PDF (255KB)
DOCX (1.5MB)
Maribyrnong Street, FootscrayLate April – July 2018Investigation works between Footscray Road and Youell Street, and building demolition works at 33 Maribryrnong Street.PDF (683KB)
DOCX (384KB)
Youell Street, Footscray20 April 2018 – early 2019Parking and traffic changes on Youell Street.PDF (1.13MB)
Whitehall Street, Yarraville/FootscrayLate April 2018 – April 2019Worksites established on Whitehall Street between Parker Street and Leek Street as part of North Yarra Main Sewer diversion.23 October Update
PDF (2.58MB)
DOC (2.58M)
Previous updates
PDF (985KB)
DOC (331KB)
Whitehall Street, Yarraville and Footscray (residents and businesses)Late April 2018 – April 2019Update on planned traffic changes in your area: Whitehall Street closure and detour via Somerville Road, Hyde Street and Leek Street.PDF (848KB)
DOC (291KB)
Tunnels precinct (Whitehall Street and Hyde Street, Yarraville and Footscray)From April 2018Piling and increased activity at our Whitehall Street construction sites; utility investigations on Whitehall Street; intersection upgrades; North Yarra Main Sewer worksPDF (658KB)
DOCX (526KB)
Tunnels precinct (Whitehall Street, Yarraville and Footscray)From March 2018Ongoing work at Whitehall Street construction sitesPDF (492KB)
DOCX (389KB)

Port to City

WhereWhenWhatNotification
Dynon RoadFebruary 2020 - ongoingConstruction of the new Dynon Road shared use path and bridges over
Moonee Ponds Creek.
February 2020:
PDF (275KB)
DOCX (797KB)
E & F GateFebruary - April 2020Piling and pier construction works continue throughout E and F gate.February 2020:
PDF (268KB)
DOCX (730KB)
Maribyrnong River

Other works include:

From January 2019

Works to construct the new bridges across the Maribyrnong River, linking the West Gate Tunnel to the elevated roadway above Footscray Road.

Works include:

  • utility relocations, starting with power and done using trenching, underground drilling and cable installation
  • piling works and pier construction
  • diversion of the cycling and walking path along the Maribyrnong River from Lyons Street to Shepherd Bridge

July 2019 update:
PDF (522KB)
DOCX (1666KB)


Previous Updates:
PDF (551KB)
DOCX (115KB)
PDF (517K

Dynon RoadLate - July to DecemberWorks around Dynon Road as part of the West Gate Tunnel Project have commenced, with the start of construction for the new Dynon Road shared use path and bridges over Moonee Ponds Creek.October 2019:
PDF (613KB)
DOC (604KB)

Previous Updates

April 2019:
PDF (560KB)
DOCX (772KB)
East E Gate & F GateOctober - December 2019Construction of the new elevated road for the West Gate Tunnel Project is ongoing as piling and pier construction works continue within E and F gate.November 2019:
PDF (463KB)
DOCX (407KB)

October 2019:
PDF (607KB)
DOCX (718KB)

Previous Updates

July - September 2019:
PDF (583KB)
DOCX (791KB)

April - June 2019:
PDF (560KB)
DOCX (772KB)

Site InvestigationsMay - November 2019Over the coming months we will be continuing site investigation works within the Port to City precinct. April 2019:
PDF (386KB)
DOCX (566KB)
Docklands, Footscray, West MelbourneJanuary - April 2019Site investigations. PDF (420KB)
Footscray Road, West Melbourne19 August 2018 – February 2019First stage of construction on Footscray Road to build the new elevated road that will connect the West Gate Freeway to the CBD and CityLink.February 2020:
PDF (299KB)
DOCX (233KB)

August 2018:
PDF (280KB)
DOCX (298KB)

Wurundjeri WayOngoing until September 2018Site investigations.PDF (821KB)
DOCX (430KB)
Dynon Road, CityLink and Moonee Ponds CreekOngoing until September 2018Site investigations.PDF (628KB)
DOCX (469KB)
Footscray Road, Footscray and DocklandsLate April – July 2018Investigation works between the Maribyrnong River and Docklands, establishing a construction site at the old Melbourne Market site, and traffic changes.PDF (598KB)
DOCX (412KB)

More information

We want to keep you informed and work together to make things easier during construction.

If you have any questions about the notifications above, do not hesitate to contact us on 1800 105 105.

For more information about construction activities, read more about managing construction or come along and meet the construction team at an information session.